Westmonte Renovation Update

The Westmonte Recreation Center renovation project began in January 2018. Progress made to date includes:

  • Entire site regraded and new underground utilities installed. 
  • Excavation for both pools is complete and floors and walls have been poured.
  • Administrative building foundation has been poured and block walls are going up. 
  • Foundation excavating of the new therapeutic pool building, plumbing installation, HVAC, electrical underground pipes and conduit are underway.  

The next phase (2-3 months) is focused primarily on installing the storm water exfiltration system and getting all building exterior walls and roofs constructed. Once the buildings are weather tight, interior walls can be built to allow for electrical, plumbing, mechanical and pool work to begin.